房子在nunawading, 地相对比较平, 有1米左右sloping, 地600平,地下没有rocks, 预估site cost 四万多(不包括red zone surchage 10K), 主要是因为家附近有一个小学, 不在同一条街上,但是距离不是太远(300米), 结果henley预估的traffic management, tiger tails, 等要14k plus builder's margin 4 k, 这个价格在东区正常吗? 下面是大致的site cost 和 6 star energy rating requirement charges报价
red Zone surcharge $10,000.00
3 phase under ground power in lieu of single phase $1,419.00
electrical generator provision in case it is required $780.00
builder's margin $195.00
cut and fill a level building platform $821.00
class H1 Waffle Pod Slab in keu of class M waffle pod slab $2,300.00
provide 18 lineal metres of agricultural drains to base of cut grater than 300mm deep $540.00
provide1 no capped riser pipe to front of garage for future connection to grated drain $37.00
provide 4 no slit pits connected to agricultural drains $448.00
provision allowance for associated rock costs $1,632.00
( soil tests indicates no rock has been found on the block)
builder's margin $408.00
provide flexible drain system to suit H or P class slab $550.00
provide 86mm step down to garage in lieu of standard $450.00
provide preliminary allowance for part deepened edge beam/part bored pier footing system supporting concrete slab to satisfy founding depth & Angle $8,451.00
(cost to be confirmed after receipt of enginner's slab design
second soil test $1,262.00
provide additional cost for on site consultation and reporting for $330.00
potential tree related foundation issues to be undertaken by engineer
provide additional cost for an on site arborist consulatation and reporting for potential reee realted protection issues $1,602.00
additional fee for application for dispensation is required for council $500.00
council requirements
1) provide reticulated termite treament system part b $891.00
2) provide temporary fencing $335.00
3) mud on roads prevention as per council requirements . $343.00
Driveway over 11m long to 13. m long x 4.2 m wide
4) asset protection permit fee $210.00
rescode 3 no double glazed awning window with satinlite glazing and a restriced winder $1,116.00
OH & S requirements
1) provide preliminary amoutn for additiona lcosts for traffic management, $14,814.00
Tiger tails, material handling due to site access for crane hire
& concrete line pump if required during construction
2) bulder's margin for above $3,703.00
NBN fibre optic $672.00
6 star energy requirements $4,375.00
评论
属正常,每个builder报法不一样,但最后相差不大。
评论
谢谢啦
评论
帮顶
澳洲中文论坛热点
- 悉尼部份城铁将封闭一年,华人区受影响!只能乘巴士(组图)
- 据《逐日电讯报》报导,从明年年中开始,因为从Bankstown和Sydenham的城铁将因Metro South West革新名目而
- 联邦政客们具有多少房产?
- 据本月早些时分报导,绿党副首领、参议员Mehreen Faruqi已获准在Port Macquarie联系其房产并建造三栋投资联