Schedule of Materials for New Residential Home
To be used in conjunction with Fixed price building contract

Dated: 11/9/2013

For:​           Joe​
Site Address:​403b Gascoigne Street Hastings
Total floor Area         160m2

Terrain:​Residential
Wind Zone:​Medium
Earthquake Zone:​A



1. General

This schedule is to be read in conjunction with the accompanying drawings & specifications and build contract.

Any item in this Schedule and not shown on the drawings and visa versa shall be equally binded as though included in both.

The building will be constructed in accordance with sound trade practice, local body bylaws,relevant standard  specifications and manufacturer’s specifications,all as may be applicable.All work must comply with
NZS 3604:2011


2. Site

FOUNDATION TYPE
-Concrete slab on ground, as per plans.
If footings are required to be made deeper on council or engineers request a variation will be charged on top of contract price






3.Structure

FLOORING
         Concrete slab on ground, as per plans.

All concrete shall be 20mpa@28days and a min thickness of 100mm
While every practical effort is made for crack control in slabs, uncontrolled cracking can still happen. As it’s not structural it cannot be deemed a fault.

Slab cure: At the discretion of those on site, on the day, slab cure can be applied if thought a benefit(sika Purgo S5) to house slabs to aid curing.
                           
                     

VAPOUR BARRIER
B & A Polythene. Black Heavy Duty 0.25mm

CONCRETE MASONRY (foundations)
Manufacturer:​Firth
Width:​20 Series
Joints:​raked
Finish:​Plastered
Colour:​TBA

TIMBER FRAMING
Timber to be MSG8 grade minimum unless stated otherwise.

In general all internal & enclosed framing to be the sizes as follows:
All wall framing ​90x45 studs at 600mm crs, dwangs at 900mm crs max to suit linings and fittings.As per plan
                 
Stud Height​2.400m

Lintels​Kiln Dried Laminated timber lintel beams as required
Ceiling Battens​Timber 75x40mm FJ dry frame

MINIMUM TIMBER TREATMENT REQUIREMENTS
All timber treatment to be in accordance with NZS3602:2003

Frames & trusses​H3.2 kd
Battens behind cladding​H3.1
Plywood Bracing​H3
Valley Boards​             N/A

ROOF FRAMING
Battens​75x50 No1 Framing
Pitch​10degree
Soffit​600mm to framing

3. Enclosure

BUILDING PAPER
Tekton house wrap
Polypropylene Tape at intervals between studs that are greater than 300mm

FLEXIBLE FLASHING TAPE
Thermakraft

DAMP PROOF COURSE
Bitumac 887


     EXTERIOR CLADDING

                      - Monier Brick Matakana cream


ROOFING                                                    Coloursteel roofing corrugated longrun
Underlay:​Black Themakraft, self supporting, 215
Brand – Type:​Coloursteel
Coating:​Satin Finish

​            Barge Flashing:​.55 Coloursteel
​Other flashings:​.55 Coloursteel
Fixing:​50mm windzip screws spaced in accordance with manufacturers instructions.
Colour:​TBA


FASCIA
Material:                              Coloursteel continuous
Colour:​                        Owners choice
                       Spouting:                                 External 135mm quarter round continuous              
Finish:​
Colour:​TBA


SOFFITS
Lining:​4.5mm hardiflex as per plan
Jointing:​PVC jointers
Fixing:​40 x 2.5 galv flat head nails
Colour: ​TBA

ALUMINIUM JOINERY
Windows & Doors:​Powder coated aluminium joinery
Style:​Residential
Colour:​TBA(standard coloursteel colour)
Jambs:​19mm finger jointed H3.1 Pinus Radiata suitable to take architraves.
Jamb Finish:​Painted
Jamb Colour:​TBA
Air seal:​Gorrila Low pressure window and door
sealing foam
Air seal backing rod:​Closed cell polythene foam (PEF)
Head Height:​2025 above floor level.
Head Flashing:​Joiners to supply and coloured to match joinery
Glazing:​Metropolitan double glazed clear float glass
​Tint:          No Tint                  


Safety Glazing​All Glazing within 2000mm of bathroom floor level to be A Grade Safety Glass.

​Thickness of safety glass to be as per NZS 4223: Part 3

Obscure Glass: ​To be selected by owner
Hardware: ​Windows:
​Handles:​Standard Wedgeless located
​at sides of sash.(black)
​​
​Sliding Doors:
​Handles:​Black Milton door                    
                                                                       Hardware
​Hinged Doors:
​Handles:           Windsor range astron handle
​Hinges:             Black Milton hinges

​Colour:​TBA



ENTRANCE DOOR
Door:​                       Paint Finish timber
Style:​                        TBA
Height:​2025mm
Colour:​To owners choice
Side lights:​N/A
Hardware:​Single pull handle with snib and lock
                       
           

GARAGE DOOR
Type:​Sectional door
Style:​Colour steel
Finish:​powdercoated
Colour:​TBA
Auto Opener:​Superlift




INSULATION
Walls:​Pink Batts​2.2
Ceilings:​Pink Batts​3.2

External walls of garage to be un-insulated. Insulate internal walls between garage and dwelling​

4. INTERIOR

WALL LININGS
House:​10mm Standard Gib board fixed and stopped to level 4 suitable for paint finish.
Ensuite/Bathroom/Laundry:​10mm Gib Aqualine, fixed and stopped to level 4 suitable for paint finish.
Garage:​10mm standard Gib




CEILINGS
House:​10mm Gib Board, fixed and stopped to level 4 suitable for paint finish.
Ensuite/Bathroom:​10mm Gib Aqualine, fixed and stopped to level 4 suitable for a paint finish.
Garage:​10mm Standard Gib board, fixed and stopped to level 4 suitable for paint finish.
      SCOTIA
​                                                Cupboards & Wardrobes 40mm x 10mm                  
                                                                      MDF Scotia
                        Garage:                                  40x18 MDF Scotia
                        Remainder of house:              55mm Gib Cove
                                             
SKIRTING
House:​60x12 single bevel Pine Moulding
Laundry:​60x12 single bevel Pine Moulding
​Finish:​           Paint finish

ARCHITRAVES
House:​60mmx12mm single bevel Pine Moulding.
Laundry/ bathroom/ensuite:​60mmx12mm single bevel Pine Moulding
​Finish:​Paint finish

DOORS
Leaf:​Superior hollowcore 34mm thick panel paint quality MDF.
​Refer to drawings for sizes
Height:​2.000mm
Jambs:​19mm finger jointed Pinus Radiata suitable to take architraves.
Hardware:​Windsor series
Hinges:​Zinc plated steel – 3 per door
Leaf Finish:                             Enamel Paint
Jamb Finish:​Enamel Paint
Door Stops:​Windsor Range
Latch:                                      Windsor Tubular Latch








KITCHEN JOINERY

Refer to kitchen plan​TBA

Bench Top:​30mm engineered stone
Fronts:​Lacquared finish to owners choice of colour
Carcases:​Pre-finished white Melamine to inside of all units.
Handles:​TBA​
Sink:​Franke Pacifica PAC651
Cooktop Splashback:              Painted Glass


KITCHEN APPLIANCES:​

Oven:                                      Parmco 60cm inbuilt oven
Dishwasher:                           Parmco quietline dishwasher
Rangehood:                            Parmco 900 canopy
Wastedisposal:                        Robinhood 1.5hp
Hob:                                      Parmco electric ceramic cooktop



      STORAGE CUPBOARDS
2x full 300mm wide MDF shelves around cupboard

WARDROBES
Master Bedroom:​Pre-finished wire system fit out
                                   Or 2xfull 300mm MDF Shelves with 2xcloset rails
Other Bedrooms:​One 300mmMDF shelf and rail

MIRRORS
1.000m x 0.800m custom fitted

CEILING HATCH
                                                                  600mmx600mm MDF Panel paint finish




5. FINISH

EXTERIOR PAINTING

In accordance with manufacturers instructions.
.
Colour:​TBA​


INTERIOR PAINTING

In accordance with manufacturers instructions.
Colour:​TBA.
​1 main colour allowed for throughout.
​Change in colour in bathroom allowed for.
                       All Exposed timber 3 coats of enamel paint

Doors:           To be Finished in enamel spray finish  



FLOOR COVERINGS

Carpet & Underlay:            PC Sum $130.00lm
Floor Tiles:​     Entry/bathroom Ensuite floor                                                                               Floor tiles-                      $40.00m2 inc gst

Tiling includes :                     
                                                                     
-Kitchen
-Entryway
- Bathroom floor
- Ensuite floor
                  

Garage:                                    
-To be left plain concrete
                                 -                 





SERVICES

SPOUTING
Material:​Coloursteel
Profile:​Quarter round
Colour:​TBA

Downpipes
Brand:​            Marly
Material:​PVC
Diameter:​80mm
Finish:​Paint
Brackets:​PVC
Colour:​TB

LAUNDRY TUB
Laundry:                          Robinhood 600mm supertub
                                 


     

PLUMBING
Water pressure system:​Mains Pressure 180ltr
Water supply:​Mains Local Authority
Cold Water system:​Polybute Piping
Hot Water system:​Polybute Piping
Wastes & Vents:​PVC concealed in framing
​​Exterior Hose Taps:​3 located as per drawings.
​HWC:​Type:Mains pressure System
​Brand:​Rheem
​Size:​180ltr
​Seismic Restraint​50 x 0.6 galv strap in accordance with NZBC G12/AS1


Plumber to design water reticulation to suit.



PLUMBING FITTING
Bathroom      

Shower-1mx1m Acrylic shower                              
Toilet- Heirloom Studio 1 soft close                                          
Toilet roll holder- Studio 1 Chrome                                          
Vanity mixer- Methven Futura Chrome                                                         
Vanity-owners choice                                            
Shower mixer-Methven Futura                                                   
Shower slide-Methven Futura Satin jet Chrome                          
Heated towel rail-Serene 7bar SQ HT ladder                                
Studio 1 Tumbler Holder Chrome                                            
Bath-engilfield 1700x400                                                

Ensuite

Shower- 1mx1m Acrylic shower                                       
Toilet-   Heirloom Studio 1 soft close                                          
Vanity- owners choice                                             
Toilet roll holder- Studio 1 Chrome                                          
Shower mixer-Methven Futura                                                
Shower slide-Methven Futura Satin jet Chrome                          
Vanity mixer- Methven Futura Chrome                                       
Heated towel rail-Serene 7bar SQ HT ladder                           
Studio 1 Tumbler Holder Chrome                                            
2x32mm pop up reflex waste chrome                                      






DRAINAGE
Allow for work related to sewage, stormwater and water supply to and from new dwelling, as indicated on drawings.
Foul water connection:​Connection to council connection
Stormwater connection:​To hook into Council connection



ELECTRICAL
                       As per plan provided


1 x meter box and internal switchboard incl rcds , mcbs ,electrical inspection and cert of compliance
1
1 x inbuilt oven and hobb hookup only (extra $100 if lead and socket required)
1
1 x gas fire ppt and isolator
1
1 x HWC hookup incl hwc kit and earth bonding .
1


6 x single power points
6
21 x double power points
21
3 x phone popints
3
3 x TV points 1 being for sky
3
17 x light switches
17
2 x heat fan lights including ducting to soffitt only
2
21 x downlights Home dot 109 or similar with 100 w lamp with lamp included in costings
21
3 x 2 way switching
3
6 exterior bulkhead and lamps
6







SWITCH UNITS
​Brand:​PDL 600 Series
​Cover plate colour:​White
​Switch colour:​White

SWITCH SOCKET UNITS​
​Brand:​PDL 600 Series
​Cover plate colour:​White
​Switch colour:​White

LIGHT FITTINGS
​Internal fittings​Brand​Type
​Recessed Incandescent:​Superlux​SD100
Recessed Halogen:​CML ​009n S/S, Redback​ ​Transformer
Vanity lights                              2x halogen above

External Fittings
Recessed Halogen​CML​009n S/S, Redback​Transformer

HEATED TOWEL RAILS
​Brand:​Mantele IPX6 Heated Towel ladder
​Size:​620mmx810mmx120mm
​Colour:​Chrome

HEATING        

Daikin wall mounted heat pump unit



                                         
                                         

                                                            

                       
   7.1​VENTING & DUCTING

​Ensuite & Bathrooms:​Brand/Type: 3 in 1 heat/fan/light                           ​               

​Kitchen Rangehood: ​Supplied with appliance

​All ducting to travel through roof space and outside to soffit vent.





7.10     SECURITY                   No Allowance

                  
7.11 SMOKE DETECTORS
As per plan HPM stand alone type


7.12 TELEPHONE CONNECTION
Included in price


6. EXTERNAL


FENCING
                     1.2m high pool fence to northan boundry boardering race course
LAWNS
To be prepped and seeded

DECKING- Timber deck to extend off lounge and dinning are

-Size  24m2
-32mm Pine grip tread decking as covering




CONCRETED AREAS
Driveway/Patio​Srength:​17.5mpa
Type:​Black Oxide Coloured allowed for
​5kg per M3
           

Cutting:​expansion cuts only
Quantity:​100sqm allowed for











CBNZ 10 year Home First Builders Gauarantee Included in contract price
-Refer to attached documentation

                                                
Total Price GST Inclusive(15%)         
Full build contract    $228,450.00







                  
                                                      


Wine Country Construction Ltd

评论
160平米,3房?

评论

对三房两浴双车库

评论
不清楚Hastings的行情,在奥克兰的话,楼主贴的这个配置18万左右应该可以做下来,当然是自己管理。奥克兰在建材和人工上或许比Hastings会便宜些?洋人公司大包,这个价格我觉得还算是合理的。

评论

better have a box ceiling 2.7 meter for living room.
wall pink batt 2.5?

评论

是吗?我不懂管理,全是洋人管理

评论

160平米,18万可以吗?

评论
看楼主贴的内容,应该是平地做的传统地基,因为没有任何涉及到挡土墙、excavation的内容,两万应该够了。以这个低端的配置,地基完成后1000一平够了。

评论

是不是说配置很差,那性价比怎样?两万就够?不明白?

评论
楼主谈合同的时候,下面几点都要考虑进去哦,

1. starting and completion date (工程开始结束时间)
2. liquidated damages (延迟罚金 -  例如每天500刀罚金)
3. defect liability period (工程缺陷维修期, 商业一般6个月,民宅3个月就可以了,这段期间屋主可以竟可能的找出建筑瑕疵,然后承建商必须及时修理)
4. Retention? (工程尾款,民宅留个5%,直到defect liability period 结束,然后付清)
5. variation of conditions (变更的条款,等等,很重要)
6. Contractor's insurance detail (承建商的保险,包括 public liability 等等)
7. Payment Claim conditions (付款方式,是月付,还是10% 首期,然后最后一笔付清,还是按工程进度付款)

评论

谢谢你的宝贵意见,他还有另一个关于工期和付款细节的合同的,然后每付一次款,会有银行叫估价师评估工程再付款,!

评论

嗯, 你找的公司应该挺正规的,我说的 2-6点,你要也注意一下。
另外又想到一个,就是subcontractor's warranty,你也要和你的contractor 要啊, 例如水工的,电工的,油漆的,floor covering的, waterproofing的,等等。 就是在合同里面加一个 subcontractor's warranty list, 然后由subcontractor 直接出warranty,这样就算你的 承建商倒了,你也会有一定的保障的。

评论

谢谢您指导!合同我已经签了,但听他说假如房子有问题中途意外停工或以后公司倒闭,不用找他的!会有一个专门的协会之类的跟进的,因为他给了钱这个协会买了保险,还有我看到别人家盖的房子木方好像不是实木来的,是用胶水和木头粘在一起的,这样跟实木有什么不同

新西兰房产

震惊!原来倒灌党全都偷偷买房了!

新西兰某倒灌党大V竟然亲口承认自己已经有房了!宣传裸斩就是为了自己下一套投资房抄底!最可悲的是本打算买自住房却没主见被人当枪使最后还说声谢谢啊。 评论 刚需一直都存在,无非 ...

新西兰房产

银行也纠错?改变短期房价预测

新西兰BNZ drastically lowers house price forecast, says market had 'false start' 这个时候突然意识到了问题所在?之前不是四大行天天喊今年增长2-5% 吗? 才一个月不到就出来承认错误了? 评论 The predictio ...

新西兰房产

求指教:关于房贷利率重新锁定

新西兰谢谢了先~~ 房贷一直放在ANZ六七年了。下个月需要重新锁定房贷,请问明白人,是到期之前自己选择一个ANZ的一年期(目前好像7.14)?还是找贷款中介选一个ANZ的? 或者,请贷款中介帮 ...

新西兰房产

利率不变,准备加息

新西兰https://www.interest.co.nz/economy/127861/reserve-bank-has-left-official-cash-rate-unchanged-55-noting-domestic-inflation-slow 奄奄一息,仍要加息 评论 希望真的能加息,早死早超生。 评论 刁民!妖言惑众,煽乱房 ...

新西兰房产

811个月定存涨到了6.4%

新西兰另外MILFORD ASSETS MANAGEMENT还有一款旗舰产品,不是KIWISAVER, 不是KIWISAVER, 不是KIWISAVER。 是INVESTMENT FUND, 连续十年稳定增长。 10年收益164.02%, 年化收益率是14.02%。如果家里有老人的,你懂 ...

新西兰房产

都说房价房市爹爹爹

新西兰但我看基督城房市很好呀 很多再盖 wigram mall旁边已经开工 几十套貌似卖掉了大部分 评论 基督城房价低,付了20%首付以后,贷款也就50-70万,基本没有压力。奥克兰这几年买house的,随便 ...

新西兰房产

请教关于City的公寓

新西兰孩子要去city上学,想买个小的apartment,但是听说很多apartment都有问题啊,漏水什么的,还有产权都是租赁的, 有没有过来人分享一些信息呢,能不能买,哪个楼盘省心一些,或者还是租 ...

新西兰房产

mlgb的联储和央行

新西兰文中说的服务性通胀就是我们所说的NON TRADEABLE INFLATION 所有国家都这个样子,主要是中央政府和地方政府效率低下,导致地方债务常年堆积,必须涨RATES来增加营收,不然地方政府怕破产 ...

新西兰房产

不谈房,就说说不跟风美国的日本

新西兰这些东西太高大上,草民的我看不懂 评论 砖家说了 崩盘又要开始了,坐稳了 定存什么的,锁在最高点,或者找剑客买基金。 妥妥活镰刀,等危机过去,全球都是优质资产。 哈哈哈哈 ...

新西兰房产

怎么知道附近房子卖出了多少钱?

新西兰怎么知道附近房子卖出了多少钱?怎么估算自己的房子在当前能卖多少钱?有什么网站可看吗? 评论 realestate.co.nz。找个中介最直接,因为房子之间差异很大,一般人不明白,你自己估 ...

新西兰房产

重磅!重磅!重磅!DTI来了

新西兰https://www.interest.co.nz/personal-finance/127974/reserve-bank-says-banks-will-have-comply-new-dti-rules-july-1-while-loan new DTI the banks will have to adhere to: 20% of new owner-occupier lending to borrowers with a DTI ratio over 6; and ...